PCRB cancels award over tender committee lack of expertise

by Dalli Advocates | Sep 19, 2024 | Cases

A recent decision by the Public Contracts Review Board (PCRB) (Case 1973) highlights several key principles of public procurement law in the context of a tender for the regeneration of St Paul’s Bay, Bugibba, Qawra, Xemxija and Salina Area. Dalli Advocates assisted...

Contractors to pay €100,000 in damages for pulling out of roads contract

by Dalli Advocates | Oct 26, 2023 | Cases

The two landmark judgments have been confirmed upon appeal, ordering two contractors to pay a total of around €100,000 in pre-liquidated damages and double  the Court expenses, as the Court of Appeal deemed appeals as vexatious.  In L-Aġenzija għal...